Progress Report
Project Title: | Bison Information Network studio equipment acquisition and installation |
Proposal Number: | 0807 |
Submitter(s): | Peter Gregory (BIN) |
E-mail: | |
Submission Date: | 11/06/08 |
Report Period: | Mid-year for June 30, 2008 ending |
Fund Number: |
|
Project Description: Due to the inability to meet the stipulations of the funding approval the project has yet to begin making purchases with these funds. Specifically, construction of the studio itself has yet to begin, but will likely commence in January or thereabouts. I have contacted Stacey Winter to begin looking at the RFP process and I am working with Bruce Frantz to get the design for the studio completed so construction can begin.
Award amount: | $175,000 |
Expenses: | 0.0 |
Remaining: balance | $175,000 |
Anticipatedexpenses | $175,000 |
Comments: | There have been no expeditures for this project as of yet. |
Amended Milestones:
- Constuction completed during the Spring semester.
- Equipment ordering completed four to six weeks prior to construction end-date.
- Installation of equipment and production activies commenced during the Spring semester.
If there are any questions concerning this project feel free to contact me at peter.gregory@ndsu.edu